Monday, February 26, 2007

Short Quotes Signatures

Heizung und Bäder

In der letzten Woche wurden auf dem Fußboden zunächst Styroporplatten verlegt. Diese haben die Elektro- und Wasserinstallationen bedeckt und dienen natürlich the insulation. On these boards then the pipes for floor heating and cooling systems were installed. Furthermore, the shower stalls, the bath tub and additional radiators were installed in the bathrooms.

The site dates on Monday said the site manager a couple of unsatisfactory work performed. These have been rectified during the week directly.

Sunday, February 18, 2007

Skating How Tostirrup

Voilà

This week, the walls were plastered on the ground floor and the roof in the attic. Outside, the brickwork was grouted. On Thursday, the skeleton was then broken down and on Friday it had finally come: the tent was dismantled and we could ein richtiges Bild von unserem Haus in seiner Umgebung machen. Es wirkt so noch viel schöner, als in der räumlichen Enge des Winterzelts.

Tuesday, February 6, 2007

How Much Are Braces For Teeth In Ontario Canada

Trockenbau, Sanitär und Elektro

Seit Montag ist das Haus voll. Die Trockenbauer bauen das Dachgeschoss aus, das heißt jetzt werden die Wände für die einzelnen Räume im Dachgeschoss eingezogen. Zuvor war das Dachgeschoss eine große Fläche ohne Innenwände. Gleichzeitig werden die Leitungen und Anschlüsse für Waschbecken, Duschen, Badewanne, Toiletten, Spülbecken und Heizung erstellt. Weiterhin sind die Elektriker damit beschäftigt die Strom-, Antennen- und Netzwerkleitungen zu verlegen und die entsprechenden Wall outlets for power outlets and light switches to set into the walls.


Sunday 04 February 2007

second painting done

Finally done, the second painting the wood paneling on the outside on the roof done. The result is impressive.



then we have still managed the remaining material for loft development in the loft. Up there on the bar now stock a lot of building materials.



Saturday 03 February 2007

eaves, Fascia boards and soffits emphasize

On Saturday, we have provided the wood paneling outside of the roof with the first coat. Taping off the brick facade has this much time has gone into. On the sanded Verblendziegelsteinen was no tape. We then turned from small paper rolls with which we have caught the film between the bricks. We then had to cancel late into the night to the first coat to get ready. Many thanks again to Mario for the tireless help!

Friday 02 February 2007

material for loft development

On Friday, the remaining Material für den Spitzbodenausbau angeliefert. Zuvor hatten wir bereits die Glaswolle nach oben geschafft. Nun mussten sogenannte OSB-Platten (Mehrschichtplatten aus langen Spänen), Gipskartonplatten, Konstruktionshölzer und jede Menge Dachlatten ins Haus und nach oben befördert werden. Wir haben zunächst nur die OSB-Platten in den Spitzboden gebracht, der Rest wurde im Dachgeschoss zwischen gelagert.