Großes Update - Zimmer fertig - Fenster werden eingebaut

It's been some time since the last entry in this blog, but surely everyone will understand that we do not always give everything away. It has of course done in the meantime a lot and we have much to report. Most you will help but the many photos we have continued to diligently shot and now have found online. The progress bar right above reflects the great work.

In our last entry was just the shell reached the second floor of our apartment. Meanwhile, the complete structural work is completed. While still on the top floor, the last forms were made in our home began with the installation of the walls in the bedrooms, bathroom and toilet. These walls are now complete and the electrical cables are fed. At the moment, just all ventilation and drainage pipes are laid and since yesterday already installed the first window. Next week is beginning to install the plumbing pipes and toilet etc..